施工要求
Construction requirements
1.路沿石必须挂通线进行施工,按侧平面顶面示高标线绷紧,按线码砌侧平石,侧平石要安正,切忌前仰后合,侧面顶线顺直圆滑平顺,无高低错牙现象,平面无上下错台、内外错牙现象。
1. The construction along the road must be carried out by hanging through the line, indicating the tension of the high mark line on the top surface of the side plane, laying the side flat stone according to the line code, and keeping the side flat stone in order. Do not lean forward and backward, the side top line is straight and smooth, no high and low misalignment, no upside and downside misalignment, internal and external misalignment.
2.路沿石必须座浆砌筑,座浆必须密实,严禁塞缝砌筑;
The 2. way stone must be built in slurry and the slurry must be dense.
3.路沿石接缝处错位不超过1mm;侧石和平石必须在中间均匀错缝。
The misalignment of the 3. way along the stone joint is not more than 1mm; the side stone and the stone must be evenly sewn in the middle.
4.路沿石侧平石应保证尺寸和光洁度满足设计要求。外观美观,对弯道部分侧石应按设计半径专门加工弯道石,砌筑时保证线形流畅、圆顺、拼缝紧密。弧形侧石必须人工精凿后抛光处理。
4. sides of the side stone should ensure the size and finish to meet the design requirements. Beautiful appearance, the curved part of the side stone should be designed according to the radius of special processing curved stone, masonry to ensure smooth line, smooth, tight joint. The arc side stone must be cleaned after polishing.
5.路沿石后背应还土夯实,夯实宽度不小于50mm,厚度不小于15mm。
The 5. sides along the back of the stone should be compacted with soil. The width of the reinforcement is not less than 50mm, and the thickness is not less than 15mm.
6.路沿石勾缝:勾缝时必须再挂线,把侧石缝内的杂物剔除干净,用水润湿,然后用1:2.5水泥砂浆灌缝填实勾干。
6. Stone joints along the road: when the joints must be hung up again, the debris in the side stone joints removed clean, wet with water, and then 1:2.5 cement mortar filling joints to dry.
7.侧平石勾缝、安砌后适当浇水养护。
7. side flat stone joint, after building, proper watering and maintenance. |